1000 MW in the Test Lab

Auteur(s):
Martin Bennauer (Siemens AG), 
Achim Degenhardt (Siemens AG), 
Rüdiger Kutzner (Hochschule Hannover), 
Patrick Müller (Siemens AG), 
Christoph Schindler (Siemens AG), 
Michael Schütz (Siemens AG), 
Andree Wenzel (Hochschule Hannover), 
Société: Siemens AG, Allemagne
Hochschule Hannover, Allemagne
Publié: dSPACE Magazine 1/2012, Jun 2012

Modern digital control systems for power generation steam turbines have very complex control functions. Testing turbine control functionality during commissioning is time-consuming and expensive, so the obvious solution is to use a simulator in the test lab at an early stage of the project. This also has the advantage that critical cases can be tested with no risk to the plant, and any faults can be detected by standardized tests and remedied at an early stage – important factors for ensuring high quality standards.



Informations produit

Faire avancer l'innovation. Toujours à la pointe de l'évolution technologique.

S’abonner à nos newsletters, gérer ses abonnements ou se désabonner. La newsletter mensuelle contenant toutes les informations liées à l’aéronautique et défense.

Enable form call

At this point, an input form from Click Dimensions is integrated. This enables us to process your newsletter subscription. The form is currently hidden due to your privacy settings for our website.

External input form

By activating the input form, you consent to personal data being transmitted to Click Dimensions within the EU, in the USA, Canada or Australia. More on this in our privacy policy.